PROCEDURES FOR BUILDING PERMITS (The government's decree No. 16/2005/ND-CP dated 07 January 02, 2005, on management of work construction investment projects and the Construction Ministry's Circular No. 09 / 2005/TT-BXD May 6, 2005, guiding a number of contents of a building permit)
  Dossiers of application for construction permits and urban housing
1. An application for a building permit. Where temporary construction permit application deadline, in an application for a building permit must also be committed to work to dismantle the State made clearance.
2. A copy of the land use right papers prescribed by law for certified land.
3. Design drawings show the location ground, cut, the typical vertical; surface foundations of the work; placement or routing scheme works; system diagrams and technical connection and electricity supply water and drainage; snapshot status (for repair or renovation requires a building permit).
Authorized to issue construction permits
1. Provincial-level People's Committee shall authorize the Director of the Department of Construction issued a building permit for construction of special grade I work as assigned by management Decree quality construction; religion; works of historical and cultural; monuments, advertising, murals within the administrative boundaries under their management; works on routes, urban main street by the Committee provincial-level People's Committee regulations.
2. District-level People's Committee building permits remaining buildings and individual houses in urban areas within the administrative boundaries managed by the district, except for those specified in paragraph 1 of this Article.
3. Commune People's Committee granted permission to build individual houses in the rural population had approved construction plans within the administrative boundaries of communally managed in accordance with the district People's Committee.
Extension of building permit
1. Within 12 months from the date of issuance of a building permit that the work has not started, the building permit application to renew the building permit.
2. Dossiers of application for a building permit include:
 An application for renewal of construction permits;
The original building permit was issued.
3. Grant extension of time building permit within 5 working days after receiving complete and valid dossiers.
4. Licensing agency construction is the extension of a building permit.
Application Documents:
1.Nghi The 16 project management construction investment
2.Thong from 09/2005/TT-BXD Content Guidelines on construction permits